What's Coming

Major Upcoming Expenses

Total Upcoming

$1,399,000

10 projects through 2031

Special Levies

$984,000

Extra charges to owners

From Reserve Fund

$415,000

Covered by building savings

Expense Timeline

Estimated costs by year, colored by how they will be funded

Special Levy — extra one-time charge to ownersReserve Fund — paid from building savings

All Upcoming Expenses

20262 projects · $80,000

20273 projects · $274,000

20282 projects · $205,000

20291 project · $370,000

20301 project · $350,000

20311 project · $120,000

Special Levy Calculator

Understand what a special levy means for you personally

Total Levy

$154,000

Your Share (1 unit)

$2,852

Monthly Equivalent

$237.65/mo

if spread over 12 months

Start Saving Now

How many months do you have before the levy? We'll calculate how much to save each month.

Save this much each month

$237.65/mo

for 12 months = $2,852 total

Parkade Project Tracker

The most urgent major repair — here's where things stand

What is a parkade membrane?

Think of it as a giant waterproof blanket that sits on top of the underground parking garage. It stops rain and snowmelt from seeping into the concrete below. Without it, water gets into the concrete, causes cracks, and leads to very expensive structural damage. Replacing it now prevents much larger costs later.

Current Status

Planning Phase

Gathering contractor proposals

Proposals Received

2 of 3

Third proposal expected March 2026

Decision Timeline

2024

Depreciation report identifies membrane deterioration

Early 2025

Council begins gathering contractor proposals

Late 2025

Two proposals received; third expected

4

Mar 2026

Third proposal expected

5

Mid 2026

Council to present options at AGM or special meeting

6

Late 2026

Owner vote on special levy

7

2027

Work begins (weather permitting)

Note: All costs are estimates based on the most recent depreciation report and contractor proposals. Actual costs may vary. Special levies require a 3/4 vote of owners at a general meeting. Timelines are subject to change based on council decisions and contractor availability.